Notice under section 11 of the Arbitration and Conciliation Act 1996[CD1]
To
Builders
India Private Ltd.
7A,
Camac Street Calcutta 700 016
Dear
Sirs
Re: Arbitration of the disputes
arising out of Contract No. 3 entered with us.
1. You had entered into a Contract No. 3
with us undertaking to construct certain flats and guest houses on terms and
conditions contained in said contract.
2. You have failed to complete
construction and to make over delivery of possession of houses you had agreed
to construct on our behalf.
3. We have paid you advances and also all
your running bills. In spite of this, you are inordinately delaying the matter.
Time was of the essence of the contract. You have failed to keep the time
schedule.
4. The few apartments and guest houses
that you have constructed and agreed for joint inspection were found to be
defective and not suitable for occupation of the staff and they have not yet
been made habitable.
5. In spite of requests you have failed
and neglected to complete the work. As a result of your breach of the agreement
we have suffered losses and we are still suffering losses every day. Our huge
investment has been blocked and we have to pay interest to our Banker for the
finance obtained to make payment to you.
6. Under the clause of the said contract,
there is an agreement to refer the disputes to Arbitration of Mr. Rajib
Khaitan, Advocate of 6 S.P. Mukherjee Road, Calcutta 700 025.
7. Under the provisions of section 11 of
the Arbitration and Conciliation Act 1996 we hereby give you notice to concur
with the appointment of Mr. Rajib Khaitan, Advocate, as the Sole Arbitrator in
the matter of the differences and disputes that have arisen between the parties
herein and the same be referred for adjudication to him.
The
said disputes are, inter alia, the following:
a. Whether the construction of houses and
guest-houses under the said Contract No. 3 have been in accordance with the
contract?
b. Whether the construction has been completed
in accordance with the specification and the terms and conditions of the
contract?
c. Whether the contractor has delivered
completed houses, flats?
d. Whether the Eastern India Enterprise
has suffered any loss or damages due to non- compliance of the terms and
conditions of the contract by Builders India Private Ltd?
e. What is the damage and compensation
that the employer is entitled to get from the contractor?
Please
give your concurrence within 7 days of receipt of this letter.